Another method of measuring the value of a resistor is the Wheatstone bridge. This device sets up a parallel resistor system that measures the differences in voltage between two legs of a circuit. If there is a difference of voltage between the branches it will be detected by the galvanometer. A special type of Wheatstone bridge is a slide wire bridge. The setup for a slide wire bridge is shown in Figure 1. In this case there is a wire of constant resistivity with a contact that can move over the entire length.
Clik here to view.

Wheatstone bridge method for measurement of resistance
The resistance of the lengths of wire created by moving the contact is proportional to the length of the wire. So, expressing the resistance in terms of the wire length we have,
R2/R1 = L2/L1
If you are trying to determine the resistance of an unknown resistor and you have a known resistance available, the value of the unknown resistor is,
R2 = (L2/L1) R1
Where R1 is a specified resistance.
Procedure:
Ammeter – Voltmeter Method:
1. Measure the resistance of an unknown resistor using an ohmmeter.
2. With the help of your instructor set up a circuit using the unknown resistor as
shown in Figure 1. Turn on the power.
3. Measure the current flowing through the resistor.
4. Measure the voltage across the resistor
5. Calculate the value of the unknown resistor using Ohm’s Law.
6. Find the % difference between your two values.
Wheatstone Bridge Method:
1. Set up a slidewire bridge circuit as shown in Figure 2. The wires connecting the
resistances and the bridge should be as short as practically possible. Use a decade
box with a known resistance as R1. This should be set to a value about equal to
R2 (as measured by an ohmmeter). You can test this value by changing the decade
box resistance and testing the bridge balance point until it is near the center of the
bridge. Contact is made to the wire by sliding contact key C. Do not slide the key
along the wire while it is pressed down. This will scrape the wire causing it to be
nonuniform. Have the instructor check your wiring before activating the circuit.
2. Activate the circuit by closing the switch S, and balance the bridge by moving the
slide wire contact. Open the switch and record R1, L1, and L2. Leave the switch
open unless actually making measurements.
3. Repeat procedure 1 for R1 settings of (a) R1 3 R2 and (b) R1 0.3 R2 .
4. Compute the value of R2 for each case and find the average value. Compare this
value to the directly measured value of R2 by finding the percent difference.
5. Repeat the previous procedures with a large known resistance R1 and record your findings.
Image may be NSFW.
Clik here to view.

Clik here to view.